Installing Pathway Fines
Install MIGHTY109 Pathway fines on a compacted or solid base (base rock or concrete pad). If the area will be driven on, base rock should be 3-4 inches or more. Spread Pathway fines evenly over the area at a 3/4" depth or more. Water the pathway fines so that water reaches the bottom layers, but not so much as it puddles. Compact with tamper or roller. Let dry 24-48 hours.
Adding stabilizer or pre-stabilized pathway fines:
Stabilizer can be used to reduce dust and washout in DG. The stabilizer should be blended into the Pathway Fines prior to installing. Mix 1/4 to 1/2 jar of MIGHTY109 DG Stabilizer to 1 bag (40 LBS) Pathway Fines or 10-12 lbs to 2 tons. Once mixed, the pathway fines can be installed as instructions above.